Contract No: HK/2015/01 Wanchai
Development Phase II and Central Wanchai Bypass Sampling,
Field Measurement and Testing Work (Stage 3) Environmental Permit
no. EP-376/2009, Further Environmental
Permits No. FEP-01/376/2009 and FEP-02/376/2009 Monthly
Environmental Monitoring & Audit Report
- juLY 2018 -
|
CLIENTS: |
|
Civil Engineering and Development Department |
Lam
Geotechnics Limited 11/F Centre Point 181-185
Gloucester Road, Wanchai, H.K. Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail:
info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond
Dai Environmental
Team Leader |
|
DATE: |
|
August 2018 |
2.2 Scope of the Project and Site
Description
2.3 Project Organization and Contact
Personnel
3 status
of regulatory compliance
3.1 Status of Environmental Licensing and Permitting under the Project
5.2 Air Quality Monitoring Results
6.3 Review of the Reasons for and the
Implications of Non-compliance
6.4 Summary of action taken in the event of and
follow-up on non-compliance
7 Cumulative
Construction Impact due to the Concurrent Projects
9 Complaints, Notification of Summons and
Prosecution
lIST OF TABLES
Table 2.1 Schedule 2
Designated Projects under this Project
Table 2.2 Contact Details of Key Personnel
Table 3.2 Cumulative Summary of Valid Licences and
Permits under Contract no. HK/2012/08
Table 3.3 Summary of submission status under FEP-01/376/2009 Condition
Table 4.1 Noise Monitoring Stations
Table 4.2 Air Quality Monitoring Stations
Table 5.1 Noise Monitoring Stations for Contract no.
HK/2012/08
Table 5.2 Air Quality Monitoring Station for Contract
no. HK/2012/08
Table 5.3 Details of Waste Disposal for Contract no. HK/2012/08
Table 8.1 Summary of Environmental Inspections for
Contract no. HK/2012/08
Table 9.1 Cumulative Statistics on Complaints
Table 9.2 Cumulative Statistics on Successful
Prosecutions
LIST OF FIGURES
Figure
2.1 Project Layout
Figure 2.2 Project Organization Chart
Figure 4.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix 5.1 Monitoring Schedule for Reporting Month and Coming
month
Appendix 5.2 Noise Monitoring
Results and Graphical Presentations
Appendix 5.3 Air Quality Monitoring Results and
Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Notification
of Exceedance
Appendix
9.1 Complaint Log
Appendix 10.1 Construction Programme of Individual Contracts
Contract no. HK/2012/08 – Wan
Chai Development Phase II – Central- Wan Chai Bypass at Wan Chai West
·
Drainage
·
Roadworks
Noise Monitoring
Air Quality Monitoring
Complaints, Notifications of
Summons and Successful Prosecutions
Site Inspections and Audit
Future Key Issues
Contract no. HK/2012/08 – Wan Chai Development
Phase II – Central- Wan Chai Bypass at Wan Chai West
·
Roadworks
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed take up the role as the
Environmental Team (ET) under Environmental Permit no. EP-376/2009 and Further
Environmental Permits no. FEP-01/376/2009 and FEP-02/376/2009 to implement the
Environmental Monitoring and Audit (EM&A) programme as stipulated in the
EM&A Manual of the approved Environmental Impact Assessment (EIA) Report
for Wan Chai Development Phase II and Central-Wan Chai Bypass (Register No.:
AEIAR-458/2008).
1.1.2.
This report documents the finding of EM&A
works for Environmental Permit (EP) no. EP-376/2009
and Further Environmental Permits no. FEP-01/376/2009 and FEP-02/376/2009, during the period of 27th June 2018
to 26th July 2018. The cut-off date of reporting is the 26th
of each reporting month.
Section
1 Introduction –
details the scope and structure of the report.
Section
2 Project
Background – summarizes background and scope of the project, site
description, project organization and contact details of key personnel during
the reporting period.
Section
3 Status of Regulatory Compliance –
summarizes the status of valid Environmental Permits / Licenses during the
reporting period.
Section
4 Monitoring
Requirements – summarizes all monitoring parameters, monitoring
methodology and equipment, monitoring locations, monitoring frequency, criteria
and respective event and action plan and monitoring programmes.
Section
5 Monitoring
Results – summarizes the monitoring results obtained in the
reporting period.
Section
6 Compliance Audit – summarizes the auditing of monitoring
results, all exceedances environmental parameters.
Section
7 Cumulative Construction Impact due
to the Concurrent Projects – summarizes the relevant cumulative construction
impact due to the concurrent activities of the concurrent Projects.
Section
8 Environmental Site Audit –
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a
review of any
relevant follow-up actions
within the reporting period.
Section
9 Complaints, Notification of
summons and Prosecution – summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section
10 Conclusion
2.1.1
Wan Chai Development phase II and Central-Wan
Chai Bypass (hereafter called “the Project”) are Designated Project (DP) under
the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The
Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II
and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) has been approved on
11 December 2008.
2.2.1.
The design and construction of Wan Chai
Development Phase II and Central Wanchai Bypass involves the construction and
operation of primary and district distributor roads that is shown at Figure 2.1.
2.2.2.
The key purpose of the study area encompasses the Wan Chai harbourfront area. The area starts
at the boundary of Central Reclamation Phase III (CRIII) at the west and
connects to the existing Hung Hing Road at the east. The scope of the project includes:
·
A dual 2-lane
primary distributor road, Road P2, approximately 0.6km in length; and
·
Other new
primary and district distributor roads connecting to the slip roads of the
Central-Wan Chai Bypass with a total length of approximately 0.7km.
2.2.3.
The project also contains various Schedule 2 DP that, under the EIAO,
require Environmental Permits (EPs) to be granted by the DEP before they may be
either constructed or operated. Table 2.1 summarises the DP under
this Project. Figure
2.1 shows the locations of these
Schedule 2 DP.
Table
2.1 Schedule 2 Designated
Project under this Project
Item |
Designated Project |
EIAO Reference |
DP2 |
Road P2 and
other roads which are classified as primary/district distributor roads |
Schedule 2,
Part I, A.1 |
2.2.4.
The designated project work II (DP2) was
awarded to China State-Leader Joint Venture HK/2012/08 (Contract Title: Wan
Chai Development Phase II Central – Wan Chai Bypass at Wan Chai West) as part
of the Project works by the Civil Engineering and Development Department
(CEDD). The construction work under Contract
no. HK/2012/08 was commenced on 13 May 2015.
2.3.1
Civil
Engineering and Development Department and Highway Department are the overall
project controllers for the Wan Chai Development Phase
II and Central-Wan Chai Bypass respectively. For
the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.3.2
The
proposed project organization and lines of communication with respect to
environmental protection works are shown in Figure
2.2. Key
personnel and contact particulars are summarized in Table 2.2:
Table 2.2 Contact Details
of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer’s
Representative for WDII |
Chief Resident
Engineer |
Ms. Gloria
Tang |
2587 1778 |
2587 1877 |
Engineer’s
Representative for CWB |
Principal
Resident Engineer |
Mr. Peter
Poon |
3922 3388 |
3912 3010 |
|
China State-
Build King Joint Venture |
Contractor
under Contract no. HK/2012/08 |
Project Director |
C. N. LAI |
9106 5806 |
2877 1522 |
Site Agent |
Mr. George Cheung |
9268 1918 |
|||
Environmental Officer |
Mr. James Ma |
9130 9549 |
|||
Environmental Supervisor |
Mr. Y.L. Ho |
9856 5669 |
|||
Ramboll Hong
Kong
Limited |
Independent Environmental Checker (IEC) |
Independent Environmental Checker (IEC) |
Mr. David
Yeung |
3465 2888 |
3465 2899 |
Lam Geotechnics Limited |
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.3.3
In
this reporting month, the principal work activities of the contract is included
as follows:
Contract no. HK/2012/08 – Wan Chai Development
Phase II – Central- Wan Chai Bypass at Wan Chai West
·
Drainage
·
Roadworks
2.3.4
In
coming reporting month, the principal work activities of the contract is
anticipated as follows:
Contract no. HK/2012/08 – Wan
Chai Development Phase II – Central- Wan Chai Bypass at Wan Chai West
·
Roadworks
3.1.1.
A summary of the current status on licences and/or permits on environmental
protection pertinent to the Project is shown in Table 3.1.
Table 3.1 Summary
of the current
status on licences and/or permits on environmental protection pertinent to the
Project
Permits
and/or Licences |
Reference
No. |
Issued
Date |
Status |
Environmental Permit |
EP-376/2009 |
13 Nov 2009 |
Valid |
Further Environmental Permit |
FEP-01/376/2009 |
31 Mar 2015 |
Valid |
Further Environmental Permit |
FEP-02/376/2009 |
1 Aug 2016 |
Valid |
3.1.2.
The current status on licences and/or permits on environmental
protection pertinent for contract no. HK/2012/08 under FEP-02/376/2009 showed
in Table 3.2. and Table 3.3
Table
3.2 Cumulative Summary of Valid Licences and
Permits under Contract no. HK/2012/08
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-01/376/2009 |
31 Mar 2015 |
N/A |
Valid |
FEP-02/376/2009 |
1 Aug 2016 |
N/A |
Valid |
|
Notification
of Works Under APCO |
355439 |
4 Feb 2013 |
N/A |
Valid |
Registration
as a Chemical Waste Producer |
5213-134-C3790-01 |
30 Jun 2016 |
N/A |
Valid |
Billing
Account under Waste Disposal Ordinance |
7016883 |
18 Feb 2013 |
N/A |
Valid |
Water Discharge Licence |
WT00018470-2014 |
6 Mar 2014 |
31 Mar 2019 |
Valid |
Construction Noise Permit |
GW-RS1168-17 |
28
Dec 2017 |
13
Jan 2018 to 12 Jul 2018 |
Expired
and superseded by GW-RS0602-18 |
GW-RS0602-18 |
10 Jul 2018 |
13 Jul 2018 to 12 Jan 2019 |
Valid |
|
GW-RS0243-18 |
27 Mar 2018 |
5 Apr 2018 to 4 Oct 2018 |
Valid |
Table 3.3 Summary of submission status under FEP-01/376/2009
Condition
EP Condition |
Submission |
Date of Submission |
Condition 2.9 |
Noise Management
Plan (Rev. 2) |
Generally in order
as commented by EPD on 27 Oct 2015 |
Condition 2.10 |
Landscape Plan
(Rev. 0) |
Generally in order
as commented by EPD on 5 Aug 2015 |
3.1.3.
Implementation status of the recommended mitigation measures during this
reporting month is presented in Appendix 3.1.
NOISE Monitoring Station
4.1.1.
The noise monitoring station for the Project is listed and shown in Table
4.1 and Figure 4.1. Appendix 4.1 shows the established Action/Limit
Levels for the monitoring works.
Table 4.1 Noise Monitoring Station
District |
Station |
Description |
Wan Chai |
M1a |
Footbridge for Ex-Harbour Road Sports Centre |
Noise Monitoring Parameters, Frequency and Duration
4.1.2.
The construction noise level shall be measured in terms of the
A-weighted equivalent continuous sound pressure level (Leq). Leq
(30 minutes) shall be used as the monitoring parameter for the time
period between 0700 and 1900 hours on normal weekdays. For all other time
periods, Leq (5 minutes) shall be employed for comparison with the
Noise Control Ordinance (NCO) criteria. Supplementary information for data auditing,
statistical results such as L10 and L90 shall also be obtained for reference.
4.1.3.
Noise
monitoring shall be carried out at all the designated monitoring stations. The
monitoring frequency shall depend on the scale of the construction activities.
The following is an initial guide on the regular monitoring frequency for each
station on a weekly basis when noise generating activities are underway:
·
One set of
measurements between 0700 and 1900 hours on normal weekdays.
Monitoring Equipment
4.1.4. As
referred to in the Technical Memorandum ™ issued under the NCO, sound level
meters in compliance with the International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be
used for carrying out the noise monitoring. Immediately prior to and following
each noise measurement the accuracy of the sound level meter shall be checked
using an acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted as valid only if the calibration level
from before and after the noise measurement agrees to within 1.0 dB.
4.1.5. Noise
measurements shall not be made in fog, rain, wind with a steady speed exceeding
5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with
a portable wind speed meter capable of measuring the wind speed in m/s.
Air Quality Monitoring Stations
4.2.1. The air
quality monitoring stations for the Project are listed and shown in Table
4.2 and Figure 4.1. Appendix 4.1 shows the
established Action/Limit Levels for the monitoring works.
Table 4.2 Air Quality Monitoring Stations
Station ID |
Description |
CMA5b |
Pedestrian Plaza |
CMA6a |
WDII PRE Site Office |
Air QUALITY Monitoring Parameters, Frequency and
Duration
4.2.2. One-hour
and 24-hour TSP levels should be measured to indicate the impacts of
construction dust on air quality. The 24-hour TSP levels shall be measured by
following the standard high volume sampling method as set out in the Title 40
of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.
4.2.3. All
relevant data including temperature, pressure, weather conditions, elapsed-time
meter reading for the start and stop of the sampler, identification and weight
of the filter paper, and any other local atmospheric factors affecting or
affected by site conditions, etc., shall be recorded down in detail.
4.2.4. For
regular impact monitoring, the sampling frequency of at least once in every
six-days, shall be strictly observed at all the monitoring stations for 24-hour
TSP monitoring. For 1-hour TSP monitoring, the sampling frequency of at least
three times in every six-days should be undertaken when the highest dust impact
occurs.
Sampling Procedure and Monitoring Equipment
4.2.5. High
volume samplers (HVSs) in compliance with the following specifications shall be
used for carrying out the 1-hour and 24-hour TSP monitoring:
·
0.6 – 1.7 m3
per minute adjustable flow range;
·
Equipped with a
timing / control device with +/- 5 minutes accuracy for 24 hours operation;
·
Installed with elapsed-time
meter with +/- 2 minutes accuracy for 24 hours operation;
·
Capable of providing
a minimum exposed area of 406 cm2;
·
Flow control
accuracy: +/- 2.5% deviation over 24-hour sampling period;
·
Equipped with a
shelter to protect the filter and sampler;
·
Incorporated with an
electronic mass flow rate controller or other equivalent devices;
·
Equipped with a flow
recorder for continuous monitoring;
·
Provided with a
peaked roof inlet;
·
Incorporated with a
manometer;
·
Able to hold and
seal the filter paper to the sampler housing at horizontal position;
·
Easily changeable
filter; and
·
Capable of operating
continuously for a 24-hour period.
4.2.6. Initial
calibration of dust monitoring equipment shall be conducted upon installation
and thereafter at bi-monthly intervals. The transfer standard shall be
traceable to the internationally recognized primary standard and be calibrated
annually. The concern parties such as IEC shall properly document the
calibration data for future reference. All the data should be converted into standard
temperature and pressure condition.
Laboratory Measurement / Analysis
4.2.7. A clean
laboratory with constant temperature and humidity control, and equipped with
necessary measuring and conditioning instruments to handle the dust samples
collected, shall be available for sample analysis, and equipment calibration
and maintenance. The laboratory should be HOKLAS accredited.
4.2.8. Filter
paper of size 8” x 10” shall be labelled before sampling. It shall be a clean
filter paper with no pinholes, and shall be conditioned in a
humidity-controlled chamber for over 24-hours and be pre-weighed before use for
the sampling.
4.2.9. After
sampling, the filter paper loaded with dust shall be kept in a clean and
tightly sealed plastic bag. The filter paper shall then be returned to the
laboratory for reconditioning in the humidity controlled chamber followed by
accurate weighing by an electronic balance with readout down to 0.1 mg. The
balance shall be regularly calibrated against a traceable standard.
4.2.10. All the
collected samples shall be kept in a good condition for 6 months before
disposal.
4.2.11. Current
calibration certificates of equipment are presented in Appendix 4.2.
5.0.1. The environmental
monitoring will be implemented based on the division of works areas of the
designated project managed under the contract with FEP applied by individual
contractors. Overall layout showing
work areas of various contracts, latest status of work commencement and
monitoring stations is shown in Figure 2.1 and Figure 4.1. The
monitoring results are presented in according to the Individual Contract(s).
5.0.2. In the
reporting month, the concurrent contract is:
Contract
no. HK/2012/08 – Wan Chai Development Phase II – Central – Wan Chai Bypass at
Wan Chai West.
5.0.3. The
environment monitoring schedules for reporting month and coming month are
presented in Appendix 5.1.
5.1.1
The
proposed division of noise monitoring station is summarized in Table
5.1 below.
Table 5.1 Noise
Monitoring Station for Contract no. HK/2012/08
Location
ID |
District |
Description |
M1a |
Wan Chai |
Footbridge
for Ex-Harbour Road Sports Centre |
5.1.2
No action
or limit level exceedance was recorded in this reporting month.
5.1.3 The noise monitoring results
measured in this reporting period are reviewed and summarized. Details of the
noise monitoring results and graphical presentation can be referred to Appendix 5.2.
5.2.1 The
proposed division of air quality monitoring stations are summarized in Table
5.2 below.
Table 5.2
Air
Quality Monitoring Station for Contract no. HK/2012/08
Station |
Description |
CMA5b |
Pedestrian Plaza |
CMA6a |
WDII PRE Site Office |
5.2.2
Due to
interruption of electricity, the 24hr TSP monitoring at Pedestrian Plaza was
rescheduled from 5 and 11 July 2018 to 6 and 12 July 2018.
5.2.3
No action
or limit level exceedance was recorded at CMA5b – Pedestrian Plaza and CMA6a –
WDII PRE Site Office in this reporting month.
5.2.4
The air quality monitoring results measured
in this reporting period are reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
5.3.1 No Inert
and non-inert C&D wastes disposed in this reporting month. Details of the
waste flow table are summarized in Table 5.3.
Table 5.3 Details of Waste Disposal for Contract no. HK/2012/08
Waste Type |
Quantity this month |
Cumulative
Quantity-to-Date |
Disposal / Dumping Grounds |
Inert
C&D materials disposed, m3 |
NIL |
NIL |
NIL |
Inert
C&D materials recycled, m3 |
NIL |
NIL |
NIL |
Non-inert
C&D materials disposed, m3 |
NIL |
NIL |
NIL |
Non-inert
C&D materials recycled, m3 |
NIL |
NIL |
NIL |
Chemical
waste disposed, kg |
NIL |
NIL |
NIL |
6.0.1. The Event
Action Plan for construction noise and air quality are presented in Appendix 6.1.
6.1.1 No action or limit level exceedance was
recorded in this reporting month.
6.2.1
Due to interruption of electricity, the
24hr TSP monitoring at Pedestrian Plaza was rescheduled from 5 and 11 July 2018
to 6 and 12 July 2018.
6.2.2 No action or limit level exceedance was
recorded at CMA5b – Pedestrian Plaza and CMA6a – WDII PRE Site Office in this
reporting month.
6.3.1 There was
no non-compliance from the site audits in the reporting period. The
observations and recommendations made in each individual site audit session
were presented in Section 8.
6.4.1 There was
no particular action taken since no non-compliance was recorded from the site
audits in the reporting period.
7.0.1. According
to the Condition 3.4 of the EP-376/2009, this section addresses the relevant
cumulative construction impact due to the concurrent activities of the current
projects including the Central Reclamation Phase III (CRIII), Wan Chai
Development Phase II (WDII), Central-WanChai Bypass (CWB), Island Eastern
Corridor Link projects (IECL) and Wan Chai Development Phase II – Central – Wan
Chai Bypass at Wan Chai East (CWB Tunnel).
7.0.2.
According
to the Final EM&A report of Central Reclamation Phase III (CRIII) for
Contract HK 12/02, the major construction activities were completed by end of
January 2014 and no construction activities were undertaken thereafter and the
water quality monitoring was completed in October 2011. As such, it is considered that there
were no cumulative construction impact due to the concurrent activities of the
current projects with the Central Reclamation Phase III (CRIII) undertaken by
contractor HK12/02 in the reporting month.
7.0.3. According to the
construction programme of Central-Wanchai Bypass at Wanchai West at the Central
Reclamation Phase III area include roadworks, drainage and seawall coping were
performed in July 2018 reporting period. As no project related exceedance were recorded
during the reporting period, cumulative construction impact due to the
concurrent activities of the current projects with the Central Reclamation
Phase III (CRIII) was considered as insignificant.
7.0.4. According
to the construction programme of Wan Chai Development Phase II, Central-Wan
Chai Bypass and Island Eastern Corridor Link projects, the major construction
activities under Wan Chai Development Phase II were road and drains
construction and removal of temporary reclamation at Wan Chai. The major
construction activities under Central-Wan Chai Bypass and Island Eastern Corridor
Link Projects were ventilation building construction junction modification at
Central; reinstatement works along Causeway Bay Typhoon Shelter, road works and
landscape works at Victoria Park; bridge construction, approach ramp
construction, landscape deck construction, drainage construction and
ventilation building construction at North Point area in the reporting period.
In addition, other non-Wan Chai Development Phase II, Central-Wan Chai Bypass
and Island Eastern Corridor Link projects were observed undertaken at Wan Chai
North and North Point area.
7.0.5. No significant air impact from construction activities was anticipated
in the reporting month. Besides, no project related exceedance was recorded
during the water, air and noise environmental monitoring events in the
reporting month. Thus, it is evaluated that the cumulative construction impact
from the concurrent projects including Central Reclamation Phase III (CRIII),
Wan Chai Development Phase II (WDII), Central-WanChai Bypass (CWB), Island
Eastern Corridor Link projects (IECL) was insignificant.
8.0.1.
Five site
inspections for Contract no. HK/2012/08 were carried out on 3, 10, 17 and 24
July 2018 in this reporting period. The results of inspection and outcome are
summarized in Table 8.1.
Table 8.1 Summary
of Environmental Inspections for Contract no. HK/2012/08
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
180703_01 |
3-Jul-18 |
Labelling
of chemical containers shall be provided for clearer identification of
chemicals on site. |
Chemical
containers were removed. |
Completion
as observed on 10 July 2018 |
180703_02 |
3-Jul-18 |
Contractor
shall provide cleaning to the entrance of site. (Expo Drive) |
Entrance
of site was observed clean. |
Completion
as observed on 10 July 2018 |
180710_01 |
10-Jul-18 |
Oil stain
should be cleared as chemical waste and shall be properly handle and
disposal (Zone C, Expo Drive) |
Chemical
containers were removed. |
Completion
as observed on 17 July 2018 |
180710_02 |
10-Jul-18 |
Covering
should be provided to idle stockpile on site. (Zone C) |
Idle
stockpile was observed covered |
Completion
as observed on 17 July 2018 |
180710_03 |
10-Jul-18 |
Contractor
shall enhance the mitigation measure including maintenance of embankment and
cleaning the mud sitting along the seawall and covering the exposed surface
to prevent surface runoff. (Seawall along P2 road) |
Embankment
was observed maintained and the mud sitting along the seawall was cleaned.
Exposed surface was covered by tarpaulin and no surface runoff was observed. |
Completion
as observed on 24 July 2018 |
180710_04 |
10-Jul-18 |
Contractor
shall provide cleaning to the entrance of site. (Lung King Street) |
Entrance
of site was observed clean. |
Completion
as observed on 17 July 2018 |
180717_01 |
17-Jul-18 |
Contractor
shall keep the public road clean. (P2 road) |
Public
road was cleaned. |
Completion
as observed on 31 July 2018 |
180724_01 |
24-Jul-18 |
Oil stain
should be cleared as chemical waste and shall be properly handle and disposal
(Zone C) |
Oil stain
was removed. |
Completion
as observed on 31 July 2018 |
9.0.1. No
environmental complaint was received in the reporting period.
9.0.2. The details of cumulative
complaint log and updated summary of complaints are presented in Appendix 9.1
9.0.3. Cumulative
statistic on complaints and successful prosecutions are summarized in Table
9.1 and Table 9.2 respectively.
Table 9.1 Cumulative
Statistics on Complaints
Reporting Period |
No. of Complaints |
Commencement works (May 2015) to last
reporting month |
0 |
July 2018 |
0 |
Total |
0 |
Table 9.2 Cumulative
Statistics on Successful Prosecutions
Environmental
Parameters |
Cumulative No.
Brought Forward |
No. of Successful
Prosecutions this month (Offence Date) |
Cumulative No.
Project-to-Date |
Air |
0 |
0 |
0 |
Noise |
0 |
0 |
0 |
Water |
0 |
0 |
0 |
Waste |
0 |
0 |
0 |
Total |
0 |
0 |
0 |
10.0.1. The
EM&A programme was carried out in accordance with the EM&A Manual
requirements, minor alterations to the programme proposed were made in response
to changing circumstances.
10.0.2. The
scheduled construction activities and the recommended mitigation measures for
the coming month are listed in Table 10.1. The construction
programmes of individual contracts are provided in Appendix 10.1.
Table
10.1 Summary of Key Construction Activities of Individual Contract(s) to be commenced
in Coming Reporting Month
Contract No. |
Key Construction Works |
Recommended Mitigation Measures |
HK/2012/08 |
·
Drainage ·
Roadworks |
·
Dust control
during dust generating works; ·
Implementation
of proper noise pollution control; and ·
Provision of
protection to ensure no runoff out of site area or direct discharge into
public drainage system. |